The Next Chapter: Phase 1 - 
Westreville

Furnishing and installation of approximately 14,669 LF of 8 inch DR21 PVC piping along with accompanying appurtenances, meter vault, site work, and erosion control near 457th Avenue between 304th Street and 307th St.

Contractor:  Winter Contracting LLC

Substantial Completion Date:  October 15, 2023

Final Completion Date:  November 15, 2023

Consecutive Construction Days:  60 Days

Estimated Starting Date:  April 2023

Estimated Completion Date:  June 2023

All Road Bores are getting fusion pipe that helps prevent leaks.  Here is the process of fusing the pipe together.  The metal plate that heats the pipe has to be heated to 400-415 degrees before being placed between the two pieces of pipe.  The operator is only allotted a 10 degree temperature difference or the pipe will not fuse properly.  Before moving the pipe off the machine it has to be cooled to 100 degrees and completely cooled before being placed underground.

Westreville Project Update Map-image.jpg

The Next Chapter: Phase 1 - 
West Phase Booster to Garfield Booster

Furnishing and installation of approximately 32,090 LF of 14 inch DR18 PVC, approximately 26,813 LF of 12 inch DR18 PVC piping, along with accompanying appurtenances, water services, PRV vault, directional drilling, site work and erosion control near 304th Street between 457th Avenue and 468th Avenue.  Also including under 1 mile of 4 inch DR18 PVC piping near 461st Avenue between 304th Street and 303rd St.

Contractor:  Winter Contracting LLC

Vermillion River Crossing Completion Date:  April 1, 2023

Substantial Completion Date:  May 13, 2024

Final Completion Date:  June 13, 2024

Consecutive Construction Days:  120 Days

Estimated Starting Date:  April 2023

Estimated Completion Date: June 2024

CRWS WTP - Garfield Booster Station - Map.jpg

The Next Chapter: Phase 1 - 
Highway 46

Due to the State of South Dakota Department of Transportation leveling Highway 46 the CRWS pipeline needs to be moved out of the right of way into private property to continuing serving the 9 customers living east of Beresford on the highway.

Contractor:  Clay Rural Water System

COMPLETED SUMMER 2023

hwy 46 3.jpg
hwy 46 1.jpg
hwy 46 2.jpg

The Next Chapter: Phase 1 - 
West Vermillion

Furnishing and installation of approximately 25,710 LF of 4 inch DR21 PVC piping along with accompanying appurtenances, site work, and erosion control near Timber Road between Meckling Road and SD Hwy 50.

Contractor:  3D Digging and Trucking LLC

COMPLETED FALL OF 2023

CRWS - West Phase - WTP - MAP.jpg

The Next Chapter: Phase 2 - 
Water Treatment Plant

Still in the funding and planning stages.  More to come as things materialize.