The Next Chapter: Phase 1 -
Westreville
Furnishing and installation of approximately 14,669 LF of 8 inch DR21 PVC piping along with accompanying appurtenances, meter vault, site work, and erosion control near 457th Avenue between 304th Street and 307th St.
​
Contractor: Winter Contracting LLC
Substantial Completion Date: October 15, 2023
Final Completion Date: November 15, 2023
Consecutive Construction Days: 60 Days
​
Estimated Starting Date: April 2023
Estimated Completion Date: June 2023
All Road Bores are getting fusion pipe that helps prevent leaks. Here is the process of fusing the pipe together. The metal plate that heats the pipe has to be heated to 400-415 degrees before being placed between the two pieces of pipe. The operator is only allotted a 10 degree temperature difference or the pipe will not fuse properly. Before moving the pipe off the machine it has to be cooled to 100 degrees and completely cooled before being placed underground.
The Next Chapter: Phase 1 -
West Phase Booster to Garfield Booster
Furnishing and installation of approximately 32,090 LF of 14 inch DR18 PVC, approximately 26,813 LF of 12 inch DR18 PVC piping, along with accompanying appurtenances, water services, PRV vault, directional drilling, site work and erosion control near 304th Street between 457th Avenue and 468th Avenue. Also including under 1 mile of 4 inch DR18 PVC piping near 461st Avenue between 304th Street and 303rd St.
​
Contractor: Winter Contracting LLC
Vermillion River Crossing Completion Date: April 1, 2023
Substantial Completion Date: May 13, 2024
Final Completion Date: June 13, 2024
Consecutive Construction Days: 120 Days
​
Estimated Starting Date: April 2023
Estimated Completion Date: June 2024
The Next Chapter: Phase 1 -
Highway 46
Due to the State of South Dakota Department of Transportation leveling Highway 46 the CRWS pipeline needs to be moved out of the right of way into private property to continuing serving the 9 customers living east of Beresford on the highway.
​
Contractor: Clay Rural Water System
COMPLETED SUMMER 2023
The Next Chapter: Phase 1 -
West Vermillion
Furnishing and installation of approximately 25,710 LF of 4 inch DR21 PVC piping along with accompanying appurtenances, site work, and erosion control near Timber Road between Meckling Road and SD Hwy 50.
​
Contractor: 3D Digging and Trucking LLC
COMPLETED FALL OF 2023
The Next Chapter: Phase 2 -
Water Treatment Plant
Still in the funding and planning stages. More to come as things materialize.